滨海金麟府5#楼工程施工组织设计
摘 要
本工程施工组织设计作为在工程施工过程组织和指导施工的技术、经济文件,施工组织设计的编制从工程施工实际出发,做到技术先进、经济实用。在确保工程进度的前提下,同时保证工程质量和生产安全的要求,从而真正做到理论指导实际生产。本工程为滨海金麟府5#楼工程,建筑总面积16805.37㎡,本工程地下2层,地上34层,建筑结构形式钢筋混凝土剪力墙结构。本设计主要包括以下内容:工程概况、施工准备工作计划、施工部署、施工现场总平面布置、施工进度计划、施工方案、主要施工机械设备和材料、劳动力配备计划、安全文明施工及环境保护措施、季节性施工措施。为确保工期、质量及安全、文明工地和节约成本等编制出针对性的施工组织设计,以指导施工顺利完成本工程项目建设,控制工程成本、质量及进度,创建优质工程。
关键词:高层 总平面布置 施工进度计划 施工方案
ABSTRCT
The engineering construction organization design as in the engineering construction process organization and guidance of the construction of technology, economic documents, the preparation of the construction organization design from the actual construction of the project, so that advanced technology, economic and practical. In the premise of ensuring the progress of the project, at the same time to ensure the quality of the project and production safety requirements, so as to truly achieve the theory to guide the actual production. This project is binhai Jinlinfu 5# building project, a total construction area of 16805.37 square meters, the project underground 2 layers, 34 layers on the ground, building structure form reinforced concrete shear wall structure. This design mainly includes the following contents: project overview, construction preparation work plan, construction deployment, construction site general layout, construction schedule plan, construction scheme, main construction machinery equipment and materials, labor force equipment plan, safe and civilized construction and environmental protection measures, seasonal construction measures. In order to ensure the construction period, quality and safety, civilized site and cost saving, etc., to prepare targeted construction organization design, to guide the construction of the successful completion of the project construction, control the project cost, quality and progress, to create high-quality projects.
Keywords: At the top General layout Construction schedule The construction plan
目 录
1 编写依据★························································1
2 工程概况及特点★·················································4
2.1 建筑概况★··················································4
2.2 结构概况★··················································4
2.3 工程招标范围·················································5
2.4 建设地点及环境特征★········································5
2.5 施工条件★··················································5
3 施工部署························································6
3.1 施工管理目标★···············································6
3.2资源配备计划★················································6
3.2.1施工进度计划★············································6
3.2.2劳动力使用计划★··········································7
3.2.3材料和设备供应计划★·····································12
3.2.4协调与配合★·············································20
3.3施工程序★···················································25
3.3.1总体施工程序★···········································25
3.3.2 基础施工程序★···········································26
3.3.3 主体结构施工程序★·······································26
3.4项目管理总体安排·············································27
3.4.1 施工组织机构★··········································27
3.4.2 项目经理部人员的分工及各职能部门的权限★················27
4 施工准备★······················································40
4.1现场准备★···················································40
4.2技术准备★···················································40
4.3劳动力准备★·················································41
4.4施工机具及设备准备★·········································41
4.5材料准备★···················································42
5 主要分部、分项工程的施工方法和施工工艺★························45
5.1 流水段的划分及施工程序★····································45
5.2 测量定位★··················································45
5.3 土方及支护工程★············································47
5.4 基础工程★··················································57
5.5 主体结构★··················································61
5.5.1 钢筋工程★··············································61
5.5.2 模板工程★··············································84
5.5.3 混凝土工程★············································95
5.5.4 脚手架工程★···········································118
5.5.5 砌筑工程★·············································135
5.6 屋面工程★·················································144
6 季节性施工措施★··············································150
7 工程质量保证措施★·············································162
7.1 质量管理制度★············································162
7.2 施工质量保证措施★·········································164
7.3 主要的质量控制点★·········································165
7.4 质量控制措施★·············································168
7.5 成品保护措施★·············································171
8 工期保证措施★·················································174
8.1 施工进度计划和关键线路的确定★····························174
8.2 工期保证措施★············································175
9 安全生产目标及保证措施★······································180
10 文明施工目标及保证措施★·····································195
11 环境保护目标保证措施★·······································201
附录★
附录1: 施工总平面布置图★······································203
附录2: 施工总进度计划网络图、横道图★··························204
参考文献························································205
致谢····························································206